3 vessel brewing system Installing tips and thoughts. I am currently in the middle of helping a client set up a new 7 barrel 3 vessel brewhouse. I decided to write down my thoughts as and then distill those in to some installing a brewery tips.

The client Coastal County Brewing Company in the US, has run a 2HL brewpub with 4HL FV’s for 5 years.

Their system couldn’t keep up with demand anymore and they knew that a larger brewery was the next step. Also, a bigger system allows them to open a few satellite bars in the city too.

3 vessel brewing system

Where the Installation is Right Now

The 3 vessel brewing system arrived already and is currently being installed. It’s a semi-automatic system with touchscreen for several commands such as how much water to add to the mash.

Going up in size to 7BBL from 2HL means a lot more pipe-work. The system has manifolds and valves allowing us to direct the water and wort where it’s needed through the stainless-steel piping.

The 3 Vessel Brewhouse Tanks

It is a 3 vessel 7 barrel brewhouse system with mash mixer, lauter tun and whirlpool kettle. We opted for a cold-water tank to work with the heat exchanger. We make hot water that goes back into the hot water tank as we are cooling the wort after the boil on the way to the Fermentation tanks.

This allows us to have a lot of water if we decide to brew two beers in one day. Or gives us a lot of hot water for cleaning. It also means less work for the glycol system when compared to a two-stage heat exchanger.

Preparing for Your Brewery Install

Before the equipment arrived, we worked with the customer and their engineers to plan the layout of the 3 vessel brewhouse. We provided them with the building floor plan then worked together on the layout of the brewery.

3 vessel brewhouse

It’s important as it makes sure they have good work flows and that the utility ports (water and electric) were placed where needed in the building build out. As well as have the drains in the most useful positions.

Greater planning and preparation with your supplier agreed on before the equipment arrives will save time, money and heartache later on.

It makes the actual install more like putting together on giant jigsaw on site. As many of the connections and pipework have been pre-prepared by the manufacturer ready for delivery.

Installing a Brewery Tips – Wrap-Up

Anyway, this was just a short entry today just noting some of my thoughts about the installation for my client so far.

The installation has been a smooth one till now as we planned ahead using good communication as much as we could.

Good communication with your equipment manufacturer – always be open and honest with your manufacturer they can be extremely helpful with the buildout phase. They want the installation to be as much of a success as you. Open, honest and direct communication is the best.

Planning– Understand what you want your brewery to be and work with the manufacturer to make sure you get the right system to reach your brewing goals.

Be Prepared – Carrying out greater planning and groundwork before the equipment delivery; the quicker, cheaper and painless the install will be.